Only One in Ten of Your MRO Materials Is Actually Being Planned. The Other Nine Are Costing You

Table of Contents

A food manufacturer with 40 plants recently pulled two numbers from SAP. The first: about 1.7 million material-plant records in the MRO master. The second: the materials under active reorder-point planning – roughly one in ten. Nobody had decided that the other 90% should sit outside planning. It had happened gradually, one plant and one year at a time.
This is the inventory problem that conventional MRO inventory optimization programmes often miss. The issue is not simply how much stock a manufacturer holds. It is how much of its material base is actually governed by a replenishment policy.

ndustrial warehouse shelves representing MRO inventory optimization and SAP material planning gaps

TL;DR

  • In many multi-plant manufacturers, only about 10% of MRO material-plant records are under active replenishment planning. The remaining records may still carry stock, value and duplicates that no reorder point will address.
  • You can establish your own ratio in SAP by comparing total material-plant records with records assigned a planning-relevant MRP type, then examining stock on hand for the unplanned set.
  • The safest starting point is not a network-wide programme. It is one plant, a structured calibration period and planner review of every recommendation before the approach is extended to other facilities.

MRO Material Planning in SAP: How Many Materials Are Actually Being Planned?

Fewer materials are actively planned than most manufacturers expect. An MRO material master expands through ordinary operational decisions: a part is created for a project, extended to a plant, purchased once and never retired. Mergers introduce additional numbering schemes. Plant autonomy creates local records for materials that may already exist elsewhere in the network.
After a decade of these decisions, the master can contain millions of material-plant combinations. Yet only the records governed by a replenishment method, such as reorder-point planning or another planning-relevant MRP type, are actively managed through those parameters. Other records may be deliberately non-stock, but many are simply outside the planning process.
The ratio is a useful diagnostic, not a universal performance benchmark. In the source example, roughly one in ten records was under active planning. A ratio closer to one in five may indicate broader planning coverage in some environments, while one in twenty points to a much larger review requirement. The right interpretation depends on the material population, operating model and the proportion intentionally managed as non-stock.
A practical first check: ask your SAP team for two counts: total material-plant records and records assigned a planning-relevant MRP type. The source draft lists VB, VM, V1, V2 and PD as examples; validate the relevant types against your SAP configuration before using them in the extract. Compare the two counts, then examine stock on hand for the unplanned set.
That comparison gives the materials team a starting point for MRO inventory analysis: the scale of the unplanned population, the stock value attached to it and the records that warrant further review.

The Cost of Unplanned MRO Inventory

An unplanned material is not necessarily an empty bin. A material can sit outside reorder-point planning and still carry stock, value on the balance sheet and have an equivalent part recorded under another number at a different plant. This is why unplanned MRO materials can create cost even when no immediate stock-out is visible.
Three costs tend to follow:

  • Dead stock and excess holdings. Materials outside active planning may retain stock without a parameter that triggers a structured replenishment or reduction review. Excess and obsolete inventory can remain in the storeroom because no planning rule is recalculating what the plant needs.
  • Duplicate purchasing across plants. The same bearing or other spare part may exist under multiple material numbers across facilities. Without a network-level view, each plant can purchase locally even when usable stock is available elsewhere. The result can be avoidable buying, transfers that are never considered and, at times, emergency procurement.
  • Planner attention directed at the visible minority. Exception messages and parameter reviews tend to concentrate on the materials already inside the planning process. The unplanned population can remain outside routine scrutiny, even when it represents substantial working capital.

These costs do not always appear as a direct write-off. They can accumulate as working capital tied up in slow-moving stock, avoidable purchase orders and material records that obscure what the network already owns.
The source draft references benchmarks of 25–40% for excess and obsolete MRO holdings and emergency purchasing premiums of 50–80%. Those figures should be supported by verifiable sources before publication; otherwise, retain the cost mechanisms without publishing the unsourced ranges.

See Your Data in Action

See what a six-week, one-plant calibration pilot could look like on your data. Book a 30-minute scoping call.

Book a non-obligatory consultation call with our delivery team to address master data management challenges

MRO Inventory Optimization Across Multiple Plants

A multi-site inventory optimization programme does not need to begin across the entire network. Starting with every plant at once increases the number of local rules, data conditions and planner exceptions that must be reconciled before the approach has been calibrated.
The manufacturers that make progress start with one representative plant. They use the first deployment to understand how planners apply criticality, safety stock, lead-time assumptions and reorder points. The configuration is reviewed against operational judgement before it is carried to the next facility.
A six-week, one-plant calibration can be structured as follows:

Period Activity Output
Week 1 Agree the data template and run a workshop with planners on current safety-stock, criticality and reorder-point practices. Documented planning rules and agreed data requirements.
Week 2 Load the plant extract and score data quality by field. Review preliminary outputs alongside current values. Baseline data-quality view and initial comparison.
Weeks 3–5 Recompute forecasts, safety stock, reorder points and min/max levels for the plant. Review overstock and understock variances and assess critical items with planners. Reviewed recommendations and documented exceptions.
Week 6 Conduct a readout with materials and reliability teams, benchmark the approach and estimate the effort required to scale. Calibrated configuration and a network scale-up estimate.

How can manufacturers identify duplicate spare parts across multiple plants?Each recommendation should carry its supporting evidence and an approve/reject decision. A rejection is not simply a failed recommendation; it records where the model’s assumptions differ from the plant’s operating reality. Planner feedback becomes part of the calibration process. The next plant can then start from a reviewed configuration rather than repeating the same discovery work.
This is the practical distinction between isolated plant-level MRO inventory management and a repeatable multi-plant spare parts management approach: local operating rules are understood first, then translated into a controlled method that can be evaluated across facilities.

MRO Inventory Planning Recommendations: What Should You Do This Week?

  1. Establish the baseline. Pull the total material-plant record count and the count assigned a planning-relevant MRP type. Calculate the share under active planning and identify the unplanned population.
  2. Quantify the exposure. For the unplanned set, examine stock on hand, inventory value and last movement date. This separates records with no stock from materials that may be tying up working capital.
  3. Choose a representative pilot plant. Prioritize a facility where transaction volume, purchase-order cancellations or inter-plant transfers could make the review operationally meaningful.
  4. Protect critical spares. Agree which critical items must be shielded from indiscriminate inventory reduction. Make the rule explicit and require every recommendation to demonstrate how it treats those items.
  5. Make recommendations explainable. Require the current parameter, proposed parameter and supporting reason to be visible side by side. If planners cannot assess the recommendation, adoption will be limited.

The objective is not to reduce every stock balance. It is to improve MRO inventory management by distinguishing justified inventory from stock that has accumulated without a current planning rationale.

How Verdantis Approaches the Planning Gap

Verdantis approaches this problem through a plant-first calibration process supported by MRO360. The work begins with the material and plant data, then evaluates planning parameters and inventory conditions against the rules used by the materials and reliability teams.
Recommendations are presented for planner review, with evidence and an approve/reject decision. That review is central to the process: the aim is to establish a configuration that reflects the plant’s operating requirements before extending it to other facilities. This supports MRO inventory reduction through better planning, stock redeployment and replenishment decisions rather than treating write-offs as the default route.
See what a six-week, one-plant calibration pilot could look like on your data. Book a 30-minute scoping call

Frequently Asked Questions

1. What are unplanned MRO materials in SAP?

An unplanned MRO material is a material-plant record that is not governed by a planning-relevant MRP type or replenishment parameter. It may still hold stock and inventory value; it is simply outside the automated replenishment logic and may be absent from routine planning reviews.

2. How do you conduct MRO inventory analysis?

Start by comparing total material-plant records with records assigned a planning-relevant MRP type. For the unplanned set, add stock on hand, inventory value and last movement date. This provides an initial view of the population, its financial exposure and its dormancy. Validate the extract and planning-type definitions against your SAP configuration.

3. How can MRO inventory reduction happen without write-offs?

Potential actions include redeploying usable stock between plants, cancelling open purchase orders where network stock can meet demand, returning eligible excess to vendors and adjusting replenishment parameters so inventory is consumed down. Write-offs may still be necessary in some cases, but they should not be assumed to be the first or only option.

4. How do you approach multi-plant MRO inventory optimization? 

Begin with one representative plant, review the data and planning rules with local teams, and calibrate recommendations through planner approval. Once the approach reflects the plant’s operating requirements, carry the reviewed configuration to other facilities and account for their local differences

5. How does MRO inventory optimization help reduce excess stock?

MRO inventory optimization analyzes demand patterns, reorder points, safety stock, supplier lead times and inventory availability to identify excess materials and improve replenishment decisions.

6. How can manufacturers identify duplicate spare parts across multiple plants?

Manufacturers can analyze material descriptions, part numbers, specifications and stock availability across facilities to identify duplicate records and opportunities for inventory consolidation or inter-plant transfers. 

7. How does MRO inventory optimization help reduce excess stock?

MRO inventory optimization analyzes demand patterns, reorder points, safety stock, supplier lead times and inventory availability to identify excess materials and improve replenishment decisions.

8. How can manufacturers identify duplicate spare parts across multiple plants?

Manufacturers can analyze material descriptions, part numbers, specifications and stock availability across facilities to identify duplicate records and opportunities for inventory consolidation or inter-plant transfers

A Two-Number Diagnostic for Your MRO Inventory

Your plants may be holding materials that have never been brought into a formal planning process. Start with two SAP counts: total material-plant records and records assigned a planning-relevant MRP type. Share the figures with Verdantis to understand what the gap may indicate and where a one-plant review could begin.
Download the MRO360 data template to see which fields the six-week pilot requires from SAP.

About the Author

Picture of Kumar Gaurav

Kumar Gaurav

As the CEO of Verdantis, Kumar plays a pivotal role in shaping the company’s strategic direction, expanding its market presence, and fostering innovation in the field of Master Data Management. Kumar is a seasoned entrepreneur and transformative leader with over two decades of experience. He specializes in guiding clients through their digital journey with innovative solutions. With a strong background in sales leadership and complex conglomerate management, Kumar excels in P&L responsibility. He is known for his strategic consultancy in retail, e-commerce, and education, and his adeptness in aligning diverse stakeholders towards common goals within matrix organizational structures.

Related Posts

Book A Demo

Download The File

Your data is 100% protected with us via our non-disclosure agreement.

MRO Master Data Management for a leading $12Bn Oil and Gas company

Oil and Gas organizations face huge unwanted costs in the form of losses, penalties and compensation due to industrial accidents, taking a sizable chunk of their revenues. One of the important reasons for failures and accidents is the breakdown of key industrial infrastructure arising from ineffective management of the material base and inefficiencies in the MRO supply chain that are highly critical for the production and maintenance cycles.

More and more organizations are now looking to establish Master Data Management (MDM) implementations in order to manage their assets through informed decision-making based on reliable data and ensure optimal industrial safety across the enterprise.

About the company:

This US based company is a global leader in providing essential mechanical components for both land and offshore drilling rigs, complete drilling and well servicing rigs, as well as a comprehensive range of tubular inspection, internal coatings, drill string equipment, lifting and handling gear, and downhole drilling tools. It also offers supply chain services through distribution centers strategically located near major drilling and production sites worldwide. With over 800 manufacturing, sales, and service centers globally and annual revenues exceeding $12 billion, the company delivers customer-focused solutions tailored to meet the energy industry’s quality, productivity, and environmental needs.

Material Master Data Challenges

The company faced significant challenges with their master data.
• Lack of consistency and standards for the master data
• Incorrect, incomplete, unclassified and outdated attribute fields of master
data High volumes of data in multiple languages
• Multiple ERP and other legacy instances across the company
• Poorly structured material descriptions
• Lack of data governance and collaboration across cross-functional divisions and locations

Solution & Results Achieved

Solution: Material Master Data Harmonization & Ongoing Maintenance

The company implemented Verdantis Material Harmonize to cleanse and enrich its historical material master data. Using AI-powered tools and the Verdantis Content Repository, the solution classified, standardized, and eliminated duplicate materials.

Once the data was harmonized, Verdantis Material Integrity was deployed for ongoing data governance. It ensured continuous data accuracy through real-time validation, AI-driven classification, and duplication prevention, maintaining high data quality across enterprise systems.

Key Actions Taken:

  • Classified 150,000 materials into 1,210 UNSPSC and 500+ HTS codes
  • Parsed and normalized unstructured material attributes
  • Eliminated duplicates and enriched material descriptions
  • Established real-time data governance and approval workflows
  • Created a centralized repository for cross-functional data access

Results Achieved:

  • Improved Data Accuracy – Eliminated duplicate and inconsistent material records
  • Enhanced Classification – Standardized materials with UNSPSC & HTS codes
    Better Inventory Management – Optimized stock visibility and usage
  • Faster Procurement & Compliance – Enabled seamless material search & regulatory adherence
  • Sustainable Data Governance – Ensured ongoing accuracy with AI-driven maintenance
  • Informed Decision-Making – Centralized data repository for improved operational efficiency

By integrating Material Harmonize & Material Integrity, the company achieved a scalable, AI-powered Master Data Management framework, ensuring long-term data consistency, efficiency, and compliance.

Your data is secure and used solely for intended purposes. We prioritize your privacy and protect your information.